Why so long between posts, people have asked?
Well, until now progress was sort of incremental. But today this reno is storming ahead, so let me explain that building is sequential and nothing can happen until each individual step has been completed. For example, once the roof was on and framing completed, framing and plumbing inspection could take place. The furnace went in - a geothermal unit despite huge price tag and mess it created when field was dug up for piping. Ducting was installed. Then insulation could start - Dr. Foam arrived in a big truck for this job -- and soon, drywall will arrive.
The night before the plumbing inspection, one of the Sonitrol security system installers drilled a hole in a pipe by mistake and water pressure fell to zero. After a wild scramble, the hole was successfully repaired and next day the inspector gave it his stamp of approval.
Amazing! The stuff you can order online! Our kitchen fan is being fedexed from Burnaby, B.C., internet marble vanity tops have been spec'd and will be delivered in 2 weeks. Whatever steps we can take to keep out of stores so as to stay in the sun at the dock, we will take!